This schedule of activities will be followed as closely as possible.
|
Last Tuesday of January |
State Technical Committee Meeting. Tribal Subcommittee and Program
Subcommittees meet in the afternoon to make recommendations on
program changes |
By
March 1 |
NRCS State Office will send the Local Work Group package to each of
the Conservation Districts and NRCS District Conservationist for
recommended changes. NRCS District Conservationists will work with
their Conservation Districts to schedule Local Work Group meetings.
|
|
Last Tuesday of April |
State Technical Committee. Review of State level priorities,
identification of priorities from other State, Tribal and Federal
agencies. |
By
August 1 |
Local Work Group recommendations will be provided to the NRCS Field
Office District Conservationist. This gives Local Work Groups 5
months to hold Local Work Group meetings. |
By
August 7 |
District Conservationists summarize the Local Work Group
recommendations and transmit the recommendations to the NRCS State
Conservationist. |
By
August 30 |
NRCS State Office will compile the recommendations from all Local
Work Groups, the State Technical Committee and subcommittees.
Program managers will meet with Program Subcommittees to develop
responses on Local Work Group recommendations. Program managers will
recommend program changes to the State Conservationist. |
|
By September 1 |
NRCS State Office will then send the Local Work Group
recommendations and NRCS proposed changes to the State Technical
Committee (which includes all Conservation District Chairs) for
review prior to the October State Technical Committee Meeting. |
|
Last Tuesday of October |
State Technical Committee will meet to make final recommendations to
the State Conservationist. |
By
November 15 |
State Conservationist will make final decisions for the program
year, and transmit those to the NRCS Field Offices and Conservation
Districts. NRCS will also maintain all of the information on the
NRCS Arizona web page for public review throughout the year. |